2004 Bond Program Scope of Work

• Construct new locker/dressing room facility
• Renovate/refurbish restrooms and concession areas
• Replace natural turf with a synthetic playing surface
• Renovate/repair irrigation system
• Repair/refurbish metal handrails
• Repair/replace existing electrical outlets and install additional outlets at field level
• Install new electrical service for scoreboard
• Renovate press box
• Construct new storage building for maintenance equipment
• Install safety and security enhancements

Phases

Current Schedule Budget General Environmental
Restroom renovations. Complete. Over budget due to unexpected upgrade requirements to water and wastewater lines.* City of Austin water conservation program will provide vouchers for replacing toilets in the project.
Renovate concession stands, construct new locker and dressing room facilitates, reconstruct press box facilities, renovate and repair irrigation system, repair handrails, repair and add electrical outlets, construct new storage building for maintenance equipment. Substantially complete. Project over budget due to change of scope.* Project had to be redesigned due to flood zone issues to meet City of Austin requirements for new field house. Construction began November 2009 coinciding with the end of football season. Work was substantially complete for start of football season fall 2010. Repairs on north driveway were completed as change order work to address continuing issues. Improvements to hot water heaters is being pursued as change order work.
Replace natural turf with synthetic playing surface. Complete. Within budget.*

*Budget for the 2004 and 2008 Bond Programs are reported as both individual project budgets and overall program budget. While specific projects may be over or under budget, the 2004 and 2008 Bond Programs remain well within the total program budget.

Photos

Click on photo for larger version.

There are no images for this project.
Find Out What's Happening at your School
SMTW TFS
1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 31
Upcoming Events
There are no events scheduled. Other Events
  For Contractors