Projects for Wooldridge

2004 Bond Program Scope of Work

• Repave service drive with concrete and construct dumpster pads
• Construct additional parking spaces at selected locations
• Replace canopy wall-mounted security light fixtures
• Reseal exterior masonry wall
• Repair/replace approximately 47,000 square feet of built-up roofing
• Replace deteriorated classroom windows
• Renovate/refurbish student group and faculty restrooms
• Replace deteriorated ventilation system controls and equipment
• Replace ventilation system equipment serving administration area
• Install additional electrical circuits in computer lab
• Install additional lighting for stairs
• Replace grease trap serving kitchen
• Replace ventilation system boiler
• Replace domestic water lines under building
• Replace water and sanitary sewer lines serving kitchen and in other selected areas
• Install elevator for access to new library
• Construct new library and expand gym and cafeteria
• Install playslab cover
• Install safety and security enhancements

2008 Bond Program Scope of Work

• Technology upgrades
• Replace dishwasher

Phases

Current Schedule Budget General Environmental
Replace canopy and exterior wall-mounted security light fixtures; replace approximately 65,000 square feet of built-up roofing; replace deteriorated windows; renovate/refurbish student and faculty restrooms; replace ventilation controls; replace grease trap; replace domestic water lines under building; install elevator for access to new library; remodel existing library; construct additional on site parking; repair canopy flashings; re-seal exterior masonry walls; replace heating, ventilation and air conditioning unit serving administration area and system boiler; install additional electrical circuits in computer lab; install additional lighting for stairs; replace furniture, fixtures and equipment in library. Substantially complete. Over budget.* Additional landscaping added as a result of minor changes to approved site plan. Austin Energy Green Building strategies are being employed.
Playslab cover. Complete. Under budget.* Grouped with five other schools.
Safety and security enhancements: closed circuit TV. Complete. Within budget.* Grouped with two other schools.
Safety and security enhancements: card reader door access and door repair. Complete. Within budget.* Grouped with two other schools.
Replace dishwasher. Complete. Within budget.* Grouped with 12 other schools.

*Budget for the 2004 and 2008 Bond Programs are reported as both individual project budgets and overall program budget. While specific projects may be over or under budget, the 2004 and 2008 Bond Programs remain well within the total program budget.

Photos

Click on photo for larger version.

There are no images for this project.