| Current |
Schedule |
Budget |
General |
Environmental |
| Install canopy flashing at corridor 310 entry; install exterior security lighting; repair/replace deteriorated exterior doors, frames and hardware; construct additional on-site parking spaces; replace deteriorated movable wall between the gym and cafeteria; install masonry control joints in interior walls at gym and cafeteria; replace deteriorated/non-functioning exhaust fans; install new air conditioning unit for counselors area; repair/refurbish heating, ventilation and air conditioning system heat pumps; install additional electrical circuits and outlets in the library. |
Complete. |
Within budget.* |
Paired with Wooten Elementary School project. |
Austin Energy Green Building strategies will be employed. |
| Repair/replace approximately 14,100 square feet in built-up roofing. |
Complete. |
Within budget.* |
Some of original scope of work was deferred to later date. |
A modified bitumen roof with a white granular surface will be installed on roof replacements to lower cooling requirements and extend the life of the roof. |
| Kitchen hood fire suppression replacement. |
Complete. |
Under budget.* |
|
|
| Safety and security enhancements: card reader door access and door repair. |
Complete. |
Within budget.* |
Grouped with two other schools. |
|
| Safety and security enhancements: closed circuit TV. |
Complete. |
Within budget.* |
Grouped with two other schools. |
|
| Provide additional electrical power for computer network upgrades. |
Complete. |
Over budget.* |
|
|
| Air conditioning improvements in technology room. |
Complete. |
Within budget.* |
|
All new mechanical systems will meet and exceed the latest energy standards. |
| Replace approximately 43,000 square feet of built-up roofing and metal canopy. |
Complete. |
Over budget.* |
Additional work not performed in 2006. |
|
| Replace heating and air conditioning cooling tower. |
Complete. |
Within budget.* |
|
System design in accordance with energy standards (ASHRA 90.1). |
| Install playslab cover. |
Complete. |
Within budget.* |
Grouped with four other schools. |
|
| Replace heating, ventilation and air conditioning system equipment at kitchen. |
Complete. |
Within budget.* |
Grouped with work at Norman Elementary School. |
Heating, ventilation and air conditioning equipment will be high efficiency and meet or exceed latest energy standards (ASHRAE 90.1, 2001). |
| Install automatic power factor correction and harmonic distortion mitigation system. |
Construction phase. |
Under budget.* |
Grouped with nine other facilities. |
|