2004 Bond Program Scope of Work
Install railing for front stairs
Repair exterior masonry walls
Repair/replace approximately 7,000 square feet of built-up roofing
Replace deteriorated windows in selected locations
Install elevator
Replace ceiling, lighting, and curtains at cafeteria stage
Replace worn floor covering in cafeteria
Replace ventilation system equipment in cafeteria
Replace grease trap
Replace deteriorated sanitary sewer and domestic water lines serving kitchen
Install playslab cover
Install safety and security enhancements
2008 Bond Program Scope of Work
Technology upgrades
Construct built-in storage units for selected classrooms
Cafeteria and kitchen improvements
Install automatic power factor correction and harmonic distortion mitigation system
Projects Funded Through Contingency Funds Critical Renovations:
Replace heating, ventilation and air conditioning equipment in kitchen
Phases
| Current |
Schedule |
Budget |
General |
Environmental |
| Kitchen hood fire suppression replacement. |
Complete. |
Under budget.* |
|
|
| Install railing for front stairs, replace 7,000 square feet of built-up roofing, replace deteriorated windows, replace grease trap, replace sewer and water lines under kitchen, install elevator, repair exterior masonry walls, replace ceiling lighting and curtains of stage, replace floors in cafeteria, replace heating and air conditioning units in cafeteria, safety and security enhancements. |
Complete. |
Under budget.* |
Grouped with O. Henry Middle School project. |
New mechanical systems will meet or exceed latest energy standards. New roof will increase thermal efficiency and solar reflectivity. |
| Install playslab cover. |
Complete. |
Within budget.* |
Grouped with six other schools. |
|
| Construct built-in storage units in selected classrooms of original building. |
Complete. |
Over budget.* |
Grouped with three other schools. |
|
| Cafeteria/kitchen renovations: install ceiling above serving line, enclose ductwork, install new handwash sink, provide new outlets for refrigerator and mixer, new enclosure for dumpster and add two sanitary inspection ports. |
Complete. |
Over budget due to additional work at some schools.* |
Grouped with projects at five other schools. |
|
| Install automatic power factor correction and harmonic distortion mitigation system. |
Construction phase.
|
Under budget.*
|
Grouped with 10 other facilities. |
|
| Replace heating, ventilation and air conditioning equipment in kitchen. |
Design phase. |
|
Grouped with three other schools. |
|
|
*Budget for the 2004 and 2008 Bond Programs are reported as both individual project budgets and overall
program budget. While specific projects may be over or under budget, the 2004 and 2008 Bond Programs remain well
within the total program budget.