2004 Bond Program Scope of Work
Install additional exterior security lighting
Improve storm/site drainage in selected areas
Repair/replace approximately 16,000 square feet of built-up roofing
Repair/replace deteriorated windows
Replace deteriorated ceiling tile and light fixtures in 200-wing restrooms
Repair/replace deteriorated doors, frames and hardware in classroom wings
Replace deteriorated exhaust fans in student and faculty classrooms
Modify/replace ventilation system equipment serving the cafeteria
Replace electrical panels
Replace main breaker panel and switchgear
Improve lighting at the library entry
Replace plumbing fixtures in student and faculty restrooms
Construct accessible student restrooms near main entry
Renovate/expand administration area
Replace selected library casework/cabinetry/furnishings
Install playslab cover
Install safety and security enhancements
2008 Bond Program Scope of Work
Technology upgrades
Install security fencing between library and 100-classroom wing
Cafeteria and kitchen improvements
Projects Funded Through Contingency Funds Critical Renovations:
Replace heating, ventilation and air conditioning equipment in gym
Phases
| Current |
Schedule |
Budget |
General |
Environmental |
| Regrade portions of site to improve drainage. |
Complete. |
Under budget. Funded with 2002 bond funds.* |
|
|
| Additional security lighting, regrade site to improve drainage; repair windows, replace and repair heating and air conditioning systems, upgrade electrical systems, improve library entry, replace plumbing fixtures, renovate administration area, install safety and security enhancements, renovate student restroom between cafeteria and 300-wing to meet accessibility standards. |
Complete. |
Within budget.* |
Paired with project at Sunset Valley Elementary School. |
Project will use green building strategies. |
| Install playslab cover. |
Complete. |
Within budget.* |
Grouped with five other schools. |
|
| New casework at library. |
Complete. |
Within budget. Replacement of carpet was funded with maintenance and operation funds.* |
Paired with library renovations at Sunset Valley Elementary School. |
|
| Replace 16,000 square feet of built-up roofing. |
Complete. |
Within budget.* |
Paired with roofing work at Sunset Valley Elementary School. |
Reflective cap sheet as appropriate. |
| Cafeteria/kitchen renovations: replace mop sink, new ceiling in storage room, enclose supply duct and add dumpster pad. |
Complete. |
Over budget due to additional work added at some schools.* |
Grouped with projects at five other schools. |
|
| Install fencing. |
Complete. |
Under budget.* |
Paired with project at Sims Elementary School. |
|
| Replace heating, ventilation and air conditioning equipment in gym. |
Design phase. |
|
Grouped with three other schools. |
|
|
*Budget for the 2004 and 2008 Bond Programs are reported as both individual project budgets and overall
program budget. While specific projects may be over or under budget, the 2004 and 2008 Bond Programs remain well
within the total program budget.
Photos
Click on photo for larger version.
| There are no images for this project. |
|
|
Find Out What's Happening at your School
Upcoming Events
There are no events scheduled.
Other Events
|