|
|
|
2004 Bond Program Scope of Work
Construct eight-classroom addition
Construct gym, cafeteria, and administration expansions
Sealcoat and restripe south parking lot
Construct concrete dumpster pad
Install additional exterior security lighting
Improve storm/site drainage at building perimeter
Repair/replace deteriorated exterior doors, frames, and hardware
Replace/reseal expansion joints in exterior masonry walls
Replace approximately 43,000 square feet of built-up roofing and metal canopy
Repair/replace damaged corridor walls in 100- and 200-wings
Replace folding partitions between selected classrooms
Refurbish/replace casework in library
Replace clock system
Refurbish/replace interior doors and hardware
Replace floor covering in music room and administration area
Renovate/refurbish student and faculty restrooms
Replace deteriorated ventilation system controls and equipment
Replace deteriorated exhaust fans in restrooms
Replace ventilation system equipment in selected locations
Connect 300/400- classroom wing to main domestic water line and to sanitary sewer main
Replace sanitary sewer line serving kitchen
Construct story-telling structre in library
Install playslab cover
Install safety and security enhancements
2008 Bond Program Scope of Work
Technology upgrades
Phases
| Current |
Schedule |
Budget |
General |
Environmental |
| Install supplemental fresh outside air system for classrooms and cafeteria heating, ventilation and air conditioning system units. |
Complete. |
Within budget. Funded with 2002 bond funds.* |
Grouped with one other school. |
|
| New eight-classroom addition, commons, gym, cafeteria and administration offices, new playslab cover, parking spaces, roofing work, heating, ventilation and air conditioning system renovation work, repair and renovation to existing building, safety and security enhancements. |
Complete. |
Over budget.* |
Asbestos abatement was needed which initially delayed the project. |
A new retention/detention pond may be required for this project; the Districts sustainability and commissioning consultants will be involved in the project. |
| Replace fire alarm system. |
Complete. |
Within budget. Funded with 2002 bond funds.* |
Grouped with two other schools. |
|
|
*Budget for the 2004 and 2008 Bond Programs are reported as both individual project budgets and overall
program budget. While specific projects may be over or under budget, the 2004 and 2008 Bond Programs remain well
within the total program budget.
Photos
Click on photo for larger version.
| There are no images for this project. |
|
|
Find Out What's Happening at your School
Upcoming Events
There are no events scheduled.
Other Events
|
For Contractors |
|
|