2004 Bond Program Scope of Work
Install additional exterior security lighting
Repair/replace deteriorated exterior doors, frames and hardware
Repair/replace approximately 30,000 square feet of built-up roofing and repair gutters and downspouts
Replace selected library casework/cabinetry/furnishings
Repair/replace cabinets in selected classrooms
Replace interior doors in 200-wing
Renovate/refurbish student and faculty restrooms
Replace grease trap serving kitchen
Replace water piping and insulation in mechanical room and crawl space under kitchen
Replace deteriorated faucets at all sinks
Install playslab cover
Install safety and security enhancements
2008 Bond Program Scope of Work
Technology upgrades
Replace heating, ventilation and air conditioning system in kitchen, cafeteria and 200- and 500-classroom wings
Cafeteria and kitchen improvements
Projects Funded Through Contingency Funds Critical Renovations:
Repair/replace plumbing
AAFR Projects:
Renovations for college preparation in-district charter school
Phases
| Current |
Schedule |
Budget |
General |
Environmental |
| Install additional exterior security lighting at north parking; repair/replace deteriorated exterior doors, frames and hardware; renovate/refurbish student and faculty restrooms; replace deteriorated water piping and insulation in mechanical room and crawl space under kitchen; repair/replace deteriorated cabinets in classrooms; replace/add furniture, fixtures and equipment control humidity in library; replace interior doors in 200 wing; demolish and remove abandoned heating, ventilation and air conditioning system equipment on roof; repair/replace security lighting in south parking lot; replace undersized grease trap at kitchen; replace deteriorated faucets at all sinks. |
Complete. |
Under budget.* |
|
Sustainability consultants will review the renovations design to determine if any input for green design and/or rebates can be accomplished with this work. |
| Repair/replace approximately 30,000 square feet of built-up roofing. |
Complete. |
Within budget.* |
|
New replacement roof systems will provide increased thermal efficiency and solar reflectivity. |
| Safety and security: closed circuit TV. |
Complete. |
Within budget.* |
Grouped with five other schools. |
|
| Safety and security: card access and door repair. |
Complete. |
Within budget.* |
Grouped with three other schools. |
|
| Install playslab cover. |
Complete. |
Within budget.* |
Grouped with four other schools. |
|
| Replace heating, ventilation and air conditioning equipment at kitchen, cafeteria and 200-300 classroom wings. |
Complete. |
Under budget.* |
300-classroom wing units replaced in lieu of the 500-classroom wing units, which were replaced by the service center. |
Heating, ventilation and air conditioning equipment will be high efficiency and meet or exceed latest energy standards (ASHRAE 90.1, 2001). |
| Cafeteria/kitchen renovations: add handwash sink, construct dumpster pad and install sampling ports. |
Complete. |
Over budget due to anticipated additional work at Highland Park Elementary School.* |
Grouped with projects at four other schools. |
|
| Repair/replace plumbing. |
Complete. |
Under budget.* |
Grouped with Zavala Elementary School. |
|
| Renovations for college preparation in-district charter school
|
Substantially complete. |
|
Grouped with Allan and Ortega elementary schools. |
|
|
*Budget for the 2004 and 2008 Bond Programs are reported as both individual project budgets and overall
program budget. While specific projects may be over or under budget, the 2004 and 2008 Bond Programs remain well
within the total program budget.