2004 Bond Program Scope of Work
Construct retaining wall and improve surface drainage on east side of building
Repair/replace floor structure joists at room 6
Refurbish/replace deteriorated exterior doors, frames, and hardware
Repair/replace approximately 22,000 square feet of built-up roofing
Repair/replace exterior window wall systems at classrooms
Repair/restore deteriorated plaster walls
Refurbish/replace worn/damaged cabinets and chalkboards in classrooms
Renovate/refurbish student and faculty restrooms
Replace toilet partitions in restroom adjacent to library
Replace deteriorated exhaust fans in restrooms, custodial closet, and teachers workroom
Replace ventilation system equipment in various locations
Install playslab cover
Install safety and security enhancements
2008 Bond Program Scope of Work
Technology upgrades
Cafeteria and kitchen improvements
Phases
| Current |
Schedule |
Budget |
General |
Environmental |
| Cafeteria renovations: Modify/add hand wash sink(s), install backflow preventers, replace door closer(s), install forced air ventilation in restroom. |
Complete. |
Over budget due to unanticipated additional work required by Health Department and Industrial Waste Department.* |
Grouped with three other schools. Additional scope required included grease traps, view ports and revised kitchen layouts. |
|
| Construct retaining wall and improve surface drainage on east side of building. Regrade portions of site. |
Complete.
|
Under budget.* |
Focus of work to eliminate water intrusion into crawlspaces, provide ventilation of crawlspaces. Grouped with three other schools. |
|
| Replace 22,000 square feet of built-up roofing. |
Complete. |
Over budget.* |
Grouped with one other school. |
White reflective roofing was used on project. |
| Repair and replace deteriorated floor joint, refurbish and replace exterior door frames and hardware, repair/replace exterior window wall systems, renovate restrooms, install playslab cover, repair plaster walls, refurbish cabinets and chalkboards in classrooms, replace exhaust fans in restrooms, install independent heating and air conditioning system for cafeteria, install safety and security enhancements. |
Complete. |
Within budget.* |
Paired with Rosedale School project. |
Recommendations of the sustainability consultant will be considered and implemented where feasible. |
|
*Budget for the 2004 and 2008 Bond Programs are reported as both individual project budgets and overall
program budget. While specific projects may be over or under budget, the 2004 and 2008 Bond Programs remain well
within the total program budget.
Photos
Click on photo for larger version.
| There are no images for this project. |
|
|