2004 Bond Program Scope of Work
Install additional exterior security lighting
Connect roof downspouts to storm sewer system
Repair/replace worn/damaged floor tile
Repair/replace deteriorated door hardware
Repair/replace approximately 20,000 square feet of built-up roofing
Renovate/refurbish student and faculty restrooms
Demolish deteriorated walls/casework, replace ceiling tile/grid as needed, add electrical circuits and replace worn floor coverings
Replace selected library casework/cabinetry/furnishings
Install playslab cover
Install safety and security enhancements
2008 Bond Program Scope of Work
Technology upgrades
Replace heating, ventilation and air conditioning system equipment in cafeteria and gymnasium and install new digital controls
Cafeteria and kitchen improvements
Install automatic power factor correction and harmonic distortion mitigation system
Projects Funded Through Contingency Funds Critical Renovations:
Replace roofing over P.E. offices and main corridor
Phases
| Current |
Schedule |
Budget |
General |
Environmental |
| Kitchen hood fire suppression replacement. |
Complete. |
Under budget.* |
|
|
| Install exterior security lighting, connect roof downspouts to underground storm sewer, renovate and refurbish restrooms, playslab cover, replace, floor tiles, hardware, walls, ceiling, floor covering, library furniture, add electrical circuits, safety and security enhancements. |
Complete. |
Over budget.* |
Grouped with two other schools. |
Project will be reviewed by energy/sustainability consultants. |
| Roof repair and replacement. |
Complete. |
Within budget.* |
|
An energy efficient reflective cap sheet will be installed, if the budget allows. |
| Cafeteria/kitchen renovations. |
Complete. |
Under budget.* |
Grouped with eight other schools. Additional work to install floor sinks at various kitchen equipment was required. |
|
| Replace heating, ventilation and air conditioning system equipment at cafeteria, gym, library and selected classrooms. |
Complete. |
Under budget. * |
|
Heating, ventilation and air conditioning equipment will be high efficiency and meet or exceed latest energy standards (ASHRAE 90.1, 2001). |
| Install storm drainage lines with inlets, install concrete service drive, move and reinstall part of track and install berm to divert on-site water flows. |
Substantially complete. |
Under budget.* |
Grouped with projects at three other schools. |
|
| Install automatic power factor correction and harmonic distortion mitigation system. |
Construction phase. |
Under budget.* |
Grouped with 10 other facilities. |
|
| Replace roofing over P.E. offices and main corridor. |
Design phase. |
|
|
|
|
*Budget for the 2004 and 2008 Bond Programs are reported as both individual project budgets and overall
program budget. While specific projects may be over or under budget, the 2004 and 2008 Bond Programs remain well
within the total program budget.