2004 Bond Program Scope of Work
Modify student drop-off and enlarge west parking lot
Install added exterior security lighting
Improve storm/site drainage at building perimeter
Repair/replace brick masonry in various locations and add masonry control joints
Repair/replace deteriorated exterior doors, frames and hardware
Repair/replace approximately 40,000 square feet of built-up roofing
Repair/replace and reseal windows in various areas
Modify/renovate ramp at cafeteria
Install elevator at west classroom wing
Relocate weight room from stage to PE classroom
Repair/replace deteriorated paneling in selected areas
Replace stage curtains
Replace science tables in selected classrooms
Replace clock system
Create one set each of accessible restrooms for students and faculty
Clean/seal tile at restrooms
Repair/replace rusting restroom partitions
Replace deteriorated ventilation system controls and equipment
Replace deteriorated exhaust fans in student and faculty restrooms
Repair/replace/modify selected ventilation system equipment
Replace motor controls and primary electrical switchgear
Replace grease trap and sanitary sewer lines serving the kitchen
Construct new fine arts addition and convert existing space into regular classrooms
Create girls athletic locker space and refurbish/remodel existing PE/athletic dressing areas
Enlarge library within existing space
Install safety and security enhancements
2008 Bond Program Scope of Work
Technology upgrades
Install elevators
Install accessibility compliant elevator
Replace dishwasher
Install automatic power factor correction and harmonic distortion mitigation system
Projects Funded Through Contingency Funds Critical Renovations:
Replace electrical panels
AAFR Projects:
North alternative education learning support centers
Create elementary grade classroom space to relieve north central elementary school overcrowding
Phases
| Current |
Schedule |
Budget |
General |
Environmental |
| Safety and security: card reader door access and door repair. |
Complete. |
Within budget.* |
|
|
| Replace roofing, gutters and downspouts and remove deteriorated brick. |
Complete. |
Under budget.* |
|
White reflective roofing was installed. |
| Divert roof and storm drainage, remove and replace brick, replace sealants, replace hollow metal window systems, replace missing lintels, repair CMU (concrete masonry unit), clean paint soffits, relocate weight room, create accessible toilets, remove ramp to meet code, clean/seal tile, install chilled and heating pipe, replace heating and air conditioning controls, replace sewer line under kitchen, replace grease trap, install new security lighting, replace or repair exterior doors and frames, repair/replace toilet partitions, replace paneling, replace science tables, replace curtains for stage, replace clock systems, replace air handling units, install new heating and air conditioning unit, install exhaust fans in restrooms, install heating boilers, install air conditioning in small gym, replace hydroponics pumps, provide supplemental air conditioning for computer room, upgrade electricity, safety and security upgrades. |
Complete. |
Over budget.* |
This project was broken out from the larger project that contained the fine arts addition in order to have most of the renovation work completed by the beginning of the 2008-2009 school year. |
Working with sustainability consultant on energy efficient heating, ventilation and air conditioning system equipment and sustainable materials and building systems. |
| Create lane to new fine arts building, provide elevator for west classroom wing, construct new fine arts building, create girls locker space, refurbish PE dressing areas, convert existing fine arts spaces to other uses, enlarge library by converting computer room and portion of teachers work room. Includes second elevator from 2008 Bond Program. |
Complete. |
Over budget.* |
Completed August 2009. |
The new addition will meet the Austin Energy two-star Green Building rating. |
| Replace dishwasher. |
Complete. |
Under budget.* |
Grouped with eight other schools. Work substantially complete prior to start of 2010-2011 school year. |
Old equipment being replaced by high efficiency unit. |
| North alternative education learning support centers. |
Complete. |
|
Grouped with 14 other schools. |
|
| Create elementary grade classroom space to relieve north central elementary school overcrowding. |
Substantially complete. |
|
|
|
| Install automatic power factor correction and harmonic distortion mitigation system. |
Construction phase.
|
Under budget.* |
Grouped with nine other facilities. |
|
| Replace electrical panels. |
|
|
|
|
|
*Budget for the 2004 and 2008 Bond Programs are reported as both individual project budgets and overall
program budget. While specific projects may be over or under budget, the 2004 and 2008 Bond Programs remain well
within the total program budget.