Projects for Fulmore

2004 Bond Program Scope of Work

• Install additional exterior security lighting
• Replace deteriorated exterior doors and hardware
• Repair/replace approximately 50,000 square feet of built-up roofing
• Refurbish/replace casework in selected science classrooms
• Replace/refurbish interior doors and hardware
• Install safety and security enhancements

2008 Bond Program Scope of Work

• Technology upgrades
• Renovate student and faculty restrooms
• Replace sanitary sewer line in 500-classroom wing
• Cafeteria and kitchen improvements
• Install automatic power factor correction and harmonic distortion mitigation system

Projects Funded Through Contingency Funds

Critical Renovations:
• Repair/replace cafeteria heating, ventilation and air conditioning equipment
AAFR Projects:
• South alternative education learning support centers

Phases

Current Schedule Budget General Environmental
Reseal perimeter of windows. Complete. Within budget. Funded with 2002 bond funds.* Paired with one other school. Make windows more energy efficient.
Renovation. New outside fresh air systems for 24 classrooms, safety and security improvements, replacing exterior door and hardware, renovate science classroom casework. Complete. Over budget. Outside air units funded with 2002 bond funds.* Paired with one other school. Applying green building components. Supplemental outside air units improved indoor air quality.
Repair/replace approximately 50,000 square feet of built-up roofing. Complete. Under budget.* Because of the ongoing roof leak problems the school wanted the construction work to start as soon as possible. New replacement roof system will provide increased thermal efficiency and solar reflectivity.
Kitchen hood fire suppression replacement. Complete. Under budget.*
Construct air-gap at sinks; modify/add handwash sinks; install backflow preventers at sinks; install forced air ventilation in restroom; replace ceiling materials/system; install splash guards at sinks; replace sanitary sewer line at 500-classroom wing; renovate student and faculty restrooms. Complete. Under budget.* Grouped with project at Zilker Elementary School. Replacement of sanitary sewer line at 500. Classroom wing had been previously replaced, so it was removed from the scope of work. Problems with the delivery and installation of toilet partitions caused the project to extend into the 2010 – 2011 school year.
South alternative education learning support centers. Complete. Grouped with 15 other schools.
Repair/replace cafeteria heating, ventilation and air conditioning equipment. Construction phase. Over budget.* Grouped with three other schools.
Install automatic power factor correction and harmonic distortion mitigation system. Construction phase. Under budget.* Grouped with 10 other facilities.

*Budget for the 2004 and 2008 Bond Programs are reported as both individual project budgets and overall program budget. While specific projects may be over or under budget, the 2004 and 2008 Bond Programs remain well within the total program budget.

Photos

Click on photo for larger version.

There are no images for this project.
Find Out What's Happening at your School
SMTW TFS
1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 31
Upcoming Events
There are no events scheduled. Other Events
  For Contractors