| Current |
Schedule |
Budget |
General |
Environmental |
| Repair/reseal walls and windows. |
Complete. |
Within budget. Funded with 2002 bond funds. Operations budget paid for the cafeteria work.* |
The presence of asbestos in the window glazing influenced the decision to replace the windows, vs. replacing the glazing. Window replacement was more cost effective and new windows in other Burnet classroom wings were installed. |
Less glass and more insulated panels will reduce the heat gain through the window wall. |
| Safety and security: card reader door access. |
Complete. |
Within budget.* |
Grouped with four other schools. |
|
| Kitchen hood fire suppression replacement. |
Complete. |
Under budget.* |
|
|
| Addition to the boys and girls athletic locker rooms, enclosing an exterior corridor, replace clock systems, expand cafeteria stage including dressing rooms and storage, renovate restrooms, install security enhancements, replace window wall system, refurbish science and fine arts casework, renovate and replace certain heating, ventilation and air conditioning equipment, install new elevator, resurface PE courts. |
Complete. |
Over budget.* |
Project started late summer 2008 due to permit delays. Skills for Living renovations completed with use of annual Maintenance & Operations (M&O) funding. |
Green products, sustainable and energy-efficient equipment and building systems will be used. |
| Replace 80,000 square feet of built-up roofing. |
Complete. |
Over budget.* |
Project delayed due to the delivery of materials. |
Employ all feasible green building strategies. |
| Safety and security: closed circuit TV. |
Complete. |
Under budget.* |
Grouped with five other schools. |
|
| Install exterior lighting and timing device. |
Complete. |
Within budget.* |
|
|
| Repair/replace roofing at 400-classroom wing, administration area, gymnasium dressing areas, and hallway corridor to industrial arts and music wing. |
Substantially complete. |
Under budget.* |
|
New replacement roof system will provide increased thermal efficiency and solar reflectivity. |
| Replace cooling tower. |
Complete. |
Over budget.* |
Grouped with project at Dobie Middle School and Andrews Elementary School. |
|
| Replace dishwasher. |
Complete. |
Under budget.* |
Exhaust hood delayed due to need to relocate a fire alarm device. Grouped with eight other schools. |
Old equipment being replaced by high efficiency unit. |
| Replace bleachers. |
Complete. |
Under budget.* |
Grouped with project at Dobie Middle School. |
|
| North alternative education learning support centers. |
Complete. |
|
Grouped with 14 other schools. |
|
| Install automatic power factor correction and harmonic distortion mitigation system. |
Construction phase.
|
Under budget.*
|
Grouped with nine other facilities. |
|