Projects for Akins

2004 Bond Program Scope of Work

• Construct classroom addition with associated parking
• Install safety and security enhancements

2008 Bond Program Scope of Work

• Technology upgrades
• Construct six-science classroom addition
• Install science safety equipment
• Install automatic power factor correction and harmonic distortion mitigation system

Projects Funded Through Contingency Funds

AAFR Projects:
• South alternative education learning support centers

Phases

Current Schedule Budget General Environmental
Construct classroom additions and associated parking. Construct outdoor covered cafeteria area. Complete. Over budget due to additional square footage and necessary renovations to existing classrooms to facilitate connection to new building.* Project was expanded from a 12-classroom to a 14-classroom addition to facilitate connection to the existing building. Components of the new Tech High program were also included. Scope of work was approved by the Campus Task Force (CTF), Internal Bond Committee (IBC) and Board of Trustees. Outdoor covered area was added to scope of work using remaining 1996 bond funds. An energy consultant was retained for this work. Implementation included shading devices, window tint, thermal wall construction, use of low VOC (Volatile Organic Compound) materials, environmentally friendly refrigerants, high efficiency lighting systems, lighting controls, water saving fixtures and building system commissioning.
Construct six-science classroom addition and acquire science safety equipment. Complete. Under budget.* Due to the renovation of existing space into some science classrooms, ten additional standard classrooms will be incorporated into the classroom addition. Site permit initially delayed due to the City’s request for floodplain easement. Completion date remains mid-August 2010. Classrooms occupied on Oct. 4, 2010, the beginning of the second six-weeks grading period. Design team met with sustainability consultant to review requirements for two-star Austin Energy Green Building requirement.
South alternative education learning support centers. Complete. Grouped with 15 other schools.
Install automatic power factor correction and harmonic distortion mitigation system. Construction phase. Under budget.* Grouped with nine other facilities.

*Budget for the 2004 and 2008 Bond Programs are reported as both individual project budgets and overall program budget. While specific projects may be over or under budget, the 2004 and 2008 Bond Programs remain well within the total program budget.

Photos

Click on photo for larger version.

There are no images for this project.
Find Out What's Happening at your School
SMTW TFS
1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 31
Upcoming Events
There are no events scheduled. Other Events
  For Contractors